ePowerBay Project Hub features battery energy storage opportunities
Explore the BESS projects featured on the platform and the upcoming milestones in the proposed schedule for Brazil’s 2026 energy storage auctions.
Brazil’s battery energy storage auctions are drawing attention to project development and opportunities for investment, acquisition and partnerships. In this context, the ePowerBay Project Hub connects project owners with investors, buyers and suppliers.
With BESS projects already published, the Hub allows users to explore technical specifications and identify opportunities for further assessment.
Discover the Project Hub
Project owners can register their developments and indicate an interest in selling, attracting investment or establishing partnerships. Registration starts with the EPE/AEGE Project Data Sheet in PDF format. The platform assists with data extraction, and the person responsible reviews the information before submission.
Publication protects commercially sensitive information: projects are presented under code names, and access to company identities and additional information depends on applicable permissions and the owner’s authorization. Companies with full access can request contact, and the owner decides whether to approve each request.
Learn more in the introduction to the ePowerBay Project Hub.
Featured projects
The following projects are under development. All report a four-hour storage duration and a connection voltage of 230 kV. The information reflects the data provided for publication.
BESS-071 — Caetité, Bahia
BESS-071 reports 108 MW of capacity submitted for technical qualification, with WEG identified as the manufacturer.
BESS-327 — Irecê, Bahia
BESS-327 reports 36 MW of capacity submitted for technical qualification, with WEG identified as the manufacturer.
BESS-150 — Jaíba, Minas Gerais
Located in Jaíba, BESS-150 reports 108 MW of capacity submitted for technical qualification, with WEG Equipamentos Elétricos S/A identified as the manufacturer.
BESS-284 — São José do Belmonte, Pernambuco
BESS-284 reports 54.687 MW of capacity submitted for technical qualification, with Hithium identified as the manufacturer.
BESS-254 — Açu, Rio Grande do Norte
BESS-254 identifies Hithium as the manufacturer and reports total energy storage capacity of 1,296 MWh.
Project images are illustrative and were generated using artificial intelligence.
Energy storage auction schedule
MME Normative Ordinance No. 136/2026 established the guidelines for two auctions: 2026 LRCAP — National Storage and 2026 LRCAP — Storage. ANEEL announced that the auctions were scheduled for December 2 and 4, 2026, with a 15-year supply period beginning in 2028. Source: ANEEL.
The schedule prepared by ePowerBay brings together the preparatory stages and upcoming planned milestones: